The quickest way to lower the electricity bill of a concrete batching plant is to stop motors from running when there is no load and to move the few drives that run continuously to the right efficiency class and speed control. The mixer, aggregate belt, cement screws, compressor and water pump all see intermittent load during a production day; a large share of the energy is lost in the minutes when no concrete is being mixed. Below we go machine by machine through where in the plant this loss occurs and what can be changed on site.
Which drives draw power during a batching cycle?
In a typical plant, once a recipe is confirmed, the aggregate bin gates open, the weigh belt discharges material into the scale, and an inclined belt or skip hoist carries the aggregate up to the mixer. At the same time the cement screws feed the cement scale from the silo, the water pump fills the water scale and the admixture pumps complete dosing. The mixer then blends the batch for a few tens of seconds, opens its gate and discharges into the truck mixer hopper.
In this cycle the time during which each drive actually carries load is short. The mixer keeps turning after discharge while it waits for the next batch, the inclined belt runs empty when a truck is late, and the compressor cuts in even at night to feed leaks in the pneumatic gates.
To reduce energy cost, these idle periods must first be made visible.
| Drive | Load pattern | Where energy is wasted | Measure that can be applied on site |
|---|---|---|---|
| Twin-shaft mixer | Heavy with a full drum, light between batches | Idle running during long waits, worn arms | Stop logic based on waiting time, arm and liner maintenance |
| Inclined aggregate belt | Continuous, varies with material quantity | Empty running while trucks wait, seized carrying idlers | Idle timeout, idler and scraper inspection |
| Cement screw | Short, intensive dosing | Running on after the scale is full, cement caked on the trough | Stop on scale signal, aeration and cleaning |
| Compressor | Load/unload cycling | Hose and valve leaks, high pressure setting | Leak survey, review of the pressure setting |
| Water and admixture pumps | Short filling | Flow set by throttling a valve | Correct pump duty point, speed control where needed |
Why does the mixer keep burning energy between batches?
The electric motor of a twin-shaft mixer is selected to shear and knead the mix in a full drum, yet for most of the day the drum is empty. The motor still turns. An idling mixer motor draws only a small fraction of its rated power, but at low load the power factor also gets worse and the compensation panel works harder. In hours when orders arrive sparsely, an automation step that stops the mixer a set time after discharge shortens this idle running.
The point to watch here is the number of starts. Each time the mixer is stopped it restarts with an empty drum; starting with a full drum strains the motor and coupling heavily, so the stop logic should only act once the drum is completely empty.
The number of starts per hour and the starting method should be agreed with the mixer manufacturer.
Worn mixing arms and liner plates are another consumption item that is often overlooked. As the gap between arms and liner opens, the mix takes longer to become homogeneous and the operator extends the mixing time. Adding an arm-gap measurement to the maintenance plan reduces both batch time and the seconds the motor runs fully loaded.

Cutting empty running on the aggregate belt and skip hoist
The inclined belt is one of the longest-running drives in the plant; even when no aggregate is being carried, operators prefer to leave the line on. Stopping the empty belt with a timeout linked to the scale discharge signal directly cuts the hours the motor turns for nothing.
A hypothetical example: if an 11 kW belt motor runs empty two hours a day drawing about 3 kW, over 250 working days a year that comes to roughly 1,500 kWh of wasted energy.
Seized carrying idlers and belt mistracking to one side also increase friction. A seized idler raises current. In winter, frozen aggregate arches at the bin outlet and loads the belt unevenly; the motor runs at higher current during this period. Checking idler bearing rotation and scraper pressure at the start of the season brings the power demanded from the motor back to normal.
In plants with a skip bucket, the hoist makes short but heavy cycles. Here the motor already runs only during movement; on the energy side, the real issue is the extra load caused by poorly maintained ropes and sheaves, plus the current peaks at starting.
If the hoist itself uses a brake motor, this duty requires a special motor; the standard range in HEM Motor's 2026 catalogue may not cover it, so send us the existing nameplate and hoist details and ask for an assessment.
Overlooked consumption at the cement screw and silo filter
The cement screw should stop once the scale is full; in many plants, however, the screw stops a few seconds after the scale signal and compacts the cement left in its trough. In humid weather this cement sticks to the wall, friction between flights and trough increases, and the electric motor draws slightly more current at every dosing. Working aeration pads at the silo outlet and periodic screw cleaning protect both energy use and dosing accuracy. A clean screw draws less current.
The dust filter fan on top of the silo and its jet cleaning system are also supplied from the compressed air line. As the filter bags clog, cleaning frequency increases and the compressor goes on load more often.
Monitoring filter differential pressure, changing bags on time and adjusting the cleaning interval to the actual pressure reduce the loss here.