In an electric motor requirements list, annual quantity is defined as the total 12-month consumption for each model, and batch size as the quantity delivered at once in one order, in separate columns. When delivery frequency and the basis of the estimate (past consumption, project, maintenance plan) are written next to them, the supplier can prepare a comparable quote from the same list.
Why are annual quantity and batch size written in separate columns?
The two figures feed different decisions. Annual quantity tells the supplier whether to plan for that model and which price tier applies; batch size relates to packaging, shipping arrangements and your own storage space.
A list with “120 pcs” in a single column can be read two ways. It could be 120 motors at once, or 120 motors spread over the year. Purchasing does not notice the ambiguity, but the supplier has to calculate for both possibilities. The quotes do not match.
An ambiguous list also spoils the comparison. One supplier prices on a single-batch assumption, another on monthly distribution. Put side by side, the difference comes from the assumption, not the product.
Which data is used to estimate annual quantity?
Annual quantity draws on three sources: past consumption, approved projects and spare requirements in the maintenance plan. Each row notes which source was used, so the supplier can see how solid the figure is.
- Past consumption: purchase or stock issue records for the last 24 months are totalled per model and halved. One-off large projects are kept separate.
- Approved project: for a machine builder, number of machines in the order book × motors per machine.
- Maintenance spare: a spare ratio is set from the installed motor count and past failure frequency.
A hypothetical example: a conveyor builder bought 70 and 90 units of a 4 kW, 4-pole model in the past two years, has approved orders for 30 machines next year and uses two motors per machine. The past average is 80, the project need 60; the overlap between the two is removed, a single annual figure is written and the note “past consumption + approved project” is added.
A figure alone is incomplete.
Adding a confidence level to the estimate helps. Three levels such as “firm”, “likely” and “option” make it easier for the supplier to decide which rows to plan for.
What is taken into account when setting batch size?
Batch size is a balance between storage space, cash flow, production or assembly schedule and shipping arrangements. A large batch lowers unit logistics cost and ties up storage and capital. A small batch gives flexibility. The number of orders rises.
A simple method: find the monthly motor consumption of the assembly line and multiply it by the number of months the store can comfortably hold. In the hypothetical example, monthly consumption is 7 units and the store holds two months of motors, so batch size is kept around 14 units. For 80 units a year that means about six batches. To price the batch, the current model pages can be checked in the HEM Motor shop.
Frame size counts too. Large-frame motors are palletised or crated; pallets and crates need floor space and forklift capacity. Frame material and size affect handling; dimensions are taken from the technical drawings page and handling and packaging information from the 2026 catalogue.
As batches grow, each motor stays longer on the shelf. In a damp store, a motor standing for months can lose winding insulation resistance and its grease settles; for large batches these storage conditions are written into the plan as well.

How are the columns of the requirements list arranged?
A good requirements list carries one model per row with all its technical and logistics information. The column layout below is easy to read on both the purchasing and the supplier side.
| Column | What to enter | Why it is needed |
|---|---|---|
| Power / poles / speed | kW, number of poles, rpm | Identity of the model |
| Frame and mounting | Frame size (e.g. 112M), B3/B5/B14/B35 | Choosing an equivalent |
| Voltage / frequency | 400 V, 50 Hz; connection | Suitability for the mains |
| Annual quantity | 12-month total | Planning and price tier |
| Batch size | Quantity per order | Packaging and shipping |
| Delivery frequency | Monthly, quarterly, call-off | Schedule |
| Basis of estimate and confidence | Past / project / maintenance; firm / likely | Sharing the risk |
Adding the application (pump, fan, conveyor, gearbox) to the list speeds up the equivalent proposal. If nameplate photos of existing motors are available, they are sent as an attachment.